Final Evaluation of Middleton Pride SRB Project
This was a comprehensive end of project evaluation of a £10million
SRB project in Greater Manchester. Our brief was to make an
assessment of the overall social, physical, and economic impact of
the programmes and to assess the nature, scope and impact of a
range of individual projects (15 in total), ranging from projects
of under £50,000 total capital and revenue spend, to two projects
that spent £879,000 and £883,000 respectively. The project used
extensive stakeholder and beneficiary research (using a mix of
methods including survey work, public events, exhibitions, focus
groups and interviews).
|
|